2 September 2015
Fourth MAS Recovery Plan Quarterly Progress Update (1 June 2015 – 31 August 2015)
One year after the launch of the MAS Recovery Plan, Malaysia Airlines Berhad commences operations, marking the official transition from MAS to MAB
Khazanah Nasional Berhad (“Khazanah”) today issued the fourth scheduled update on the ongoing restructuring of MAS for the period, 1 June 2015 to 31 August 2015. The restructuring continues to show sustained progress in all key areas under the five-year 12-point MRP announced on 29 August 2014.
The MRP Quarterly Updates are issued to provide regular updates to the public on the progress of the restructuring. The first, second and third MRP Quarterly Progress Updates were issued on 28 November 2014, 2 March 2015, and 1 June 2015 respectively.
A recap of the first nine months
Over the first nine months, strong and discernible progress was reported across the four main areas of the MRP, namely Governance and Financial Framework, Operating Business Model, Leadership and Human Capital, and Regulatory and Enabling Framework.
The major milestones achieved during the period concerned include the following:
The following are details on the progress recorded during the 1 June 2015 to 31 August 2015 period:
1. Right-sizing the workforce
Approximately 98 percent of MAS employees who were offered employment with MAB have accepted their offers. On 1 September 2015, approximately 13,000 employees commenced work at MAB. In addition, there are approximately 2,000 employees of subsidiaries such as Firefly, MASkargo and MASwings, which were not subject to the workforce right-sizing exercise.
The 13,000 MAB employees comprise approximately 9,000 employees on permanent employment, while the rest are on short-term contracts ranging from three months to 12 months.
To recap, the complete overhaul of MAS under the MRP calls for a workforce rightsizing exercise, guided by the principles of fairness, transparency and compassion. The exercise was conducted after a robust and rigorous talent selection process. With the cessation of MAS’ business, all MAS employees received termination letters beginning 1 June 2015, while over 13,000 employees were offered employment at MAB.
Employees exiting MAS were given a termination package based on a formula similar to that under their Collective Agreements. The package also includes medical benefits for 12 months post-termination, and an additional “safety net” payment to vulnerable groups – physically-challenged employees, single parents and married couples where both spouses were exiting. In addition, MAS employees who were offered and accepted employment at MAB will receive sign-on and retention payments. The respective payments will be disbursed beginning 7 September 2015.
Payments and benefits provided to employees joining MAB and those exiting MAS will cost up to RM1.5 billion in total.
2. Reskilling and redeployment
Approximately 75% of MAS employees who did not receive MAB employment offers have registered with the Corporate Development Centre (“CDC”), which began operations on 1 June 2015. CDC offers free training and outplacement services for exiting MAS employees. A wide range of services are available including talent profiling, career counseling, basic and detailed training, job-seeking skills, entrepreneurship, retirement planning and placement.
CDC has conducted career profiling, career counseling and basic training to assist registrants in the transition to a new phase of their lives. CDC has also organised career days and job interviews, with over 70 potential employers offering more than 3,000 job opportunities, including in the aviation-related sector, hospitality and business process outsourcing industries.
The CDC’s main training facility is located at the MAS Academy in Kelana Jaya in Petaling Jaya. CDC’s services are also available at the following partner facilities:
3. Conditional investment funding of up to RM6 billion and reduction of net gearing
Khazanah will soon disburse RM1.3 billion in conditional investment funding for payments related to the respective termination packages received by MAS employees under the workforce rightsizing exercise.
In total, including the RM1.3 billion mentioned, Khazanah would have disbursed a total of approximately RM3.2 billion out of the RM6 billion in conditional investment funding allocated to the restructuring effort, subject to strict conditions being met.
4. New operating business model and operational transformation
Further fine-tuning of MAB’s business plan is ongoing. More than 100 projects have been identified to reset the operating business model. They involve improving revenue, optimising cost and instituting enablers to facilitate an effective restructuring of the airline. Steps have also been taken to suspend non-profitable routes in the last three months, with further route rationalisation being considered.
The airline is on track towards becoming a sustainably profitable, principally commercial national carrier that supports national development objectives, while remaining a full-service international airline that maintains its current domestic routes and a regional “backbone” with broad global connectivity through partnerships.
5. Review of supply contracts
A comprehensive review of all MAS supply contracts has been completed, during which the contracts were identified for renegotiation, termination or novation to MAB. Several large supply contracts have been successfully renegotiated, such as the new catering agreements with Brahim’s Airline Catering Sdn Bhd. Selected foreign and local supply contracts have been novated to MAB, while the renegotiation of several others continues.
The review and renegotiation of supply contracts are crucial towards setting the airline on the path to recovery and sustained profitability.
6. Leadership
An exhaustive and comprehensive process is ongoing to identify internal and external talent for key leadership and senior management positions.
Leadership appointments made in the quarter under review were as follows:
7. Government support for key initiatives
MAB has received the necessary Air Operator Certificate (“AOC”) from the respective civil aviation authorities of the 25 countries that it is operating in, including Malaysia’s Department of Civil Aviation.
In addition, the Malaysian Aviation Commission Act 2015 passed by Parliament in April 2015 is expected to be gazetted before the end of the year. The Act provides for the establishment of an aviation commission whose key functions includes the regulation of economic matters relating to the civil aviation industry; provision of mechanisms for the protection of consumers and for dispute resolution between aviation services providers; and administration and management of public service obligations.
8. Strengthening industrial relations
Five Employee Consultative Panel (“ECP”) meetings have been held since December 2014. The meetings were attended by representatives of all recognised unions and employee associations, and representatives from non-unionised staff. In addition, there have been regular engagements with recognised unions and employee associations through other formal channels and platforms.
The ECP provides a platform to help boost alignment between employees, unions and management, and for a genuine exchange of views and ideas through dialogue and collaboration.
Concurrently, all staff are being engaged and updated on the ongoing restructuring via in-house channels such as the corporate intranet, newsletters, letters from the CEO, social media and through other direct outreach initiatives.
9. Consolidation at KLIA
The move from Subang to MAB’s headquarters in KLIA commenced in July 2015, with the first official reporting day for staff being on 17 August 2015. The headquarters is an existing facility which was renovated to accommodate the move of operations to KLIA.
10. Strengthening assurance, integrity and safety
A Governance and Reporting Framework for MAB is being designed to allow for greater employee empowerment and reduced bureaucracy.
The framework is part of the broader efforts to strengthen key control and operational systems, as called for by the MRP. These efforts include the setting up of the Governance and Ethics Committee (“GEC”), which held its first meeting in March 2015. The GEC is a sub-committee of the Board of Directors.
In addition, MAS received the Enhanced International Air Transport Association (“IATA”) Operational Safety Audit (“E-IOSA”) recertification in July 2015. MAS had in March 2015 completed a voluntary E-IOSA audit.
11. Continuous communications and stakeholder engagement
External and internal engagements and communications continue across all stakeholder groups to help ensure the smooth implementation and further progress of the restructuring effort towards a successful outcome.
The MRP Quarterly Progress Updates have been issued for the past four quarters since the launch of the MRP in August 2014. With the operationalisation of MAB on 1 September 2015, subsequent updates will be issued by the company, in line with the commitment under the MRP to provide continuous and proactive communication to stakeholders, especially the public, on the restructuring effort.
END